|
Stitch one mill one
It's been a busy summer for BAM Nuttall. Alongside its Southern
Civils Framework colleagues from Network Rail, the company
has been involved in high-profile remedial works in two tunnels
on Kent's south coast.
Only four miles apart, the structures at Abbotscliffe and
Dover Harbour both required maintenance to strengthen and
repair sections of their lining. Working closely with the
Southern Civils team and designers Donaldson Associates were
BAM Ritchies, provider of specialist geotechnical and sprayed
concrete skills.
Abbotscliffe milling
Trials were carried out in Abbotscliffe Tunnel in January
this year, with the purpose of determining the milling capabilities
of the equipment intended for use. Further development work
then took place at BAM Ritchies' depot. The main works were
successfully undertaken during a five-week blockade in July
and August, involving around-the-clock operations and a workforce
of more than 70 people.
Bored between 1840 and 1844 as part of Sir William Cubitt's
main line from Redhill to Dover, the tunnel was driven through
chalk immediately to the east of Folkestone Warren. The lining
is six bricks thick throughout. Abbotscliffe is a substantial
structure - 1 mile 182 yards long, 24 feet wide and 19 feet
6 inches high. Its alignment, close to both the cliff face
and high tide level, allowed construction to take place both
from conventional vertical shafts and 13 horizontal galleries
cut into the cliff from a road which was dug along its base.
These were used for spoil dispersal into the sea. A significant
spring, Lyddon Spout, burst through at one point and had to
be incorporated into the drainage system. When access, services
and ventilation had been established, work started with the
removal of 153m' of brickwork from the tunnel walls. This
was done by both a bespoke milling tool - fabricated from
a reduced boom - and a Webster wheel (road header) mounted
on a road-rail vehicle and hydraulic breakers carried by Case
998 RRVs. Up to 5-metre wide panels were removed using a variable
technique which allowed the spray concrete to gain sufficient
strength as well as linking into existing sprayed concrete
in the crown. These works used a site- batched dry mix which
generated more working time and increased flexibility. The
mix contained locally-sourced damp sand with high-tensile
steel fibres. Water was added at the nozzle. In total, 177mm3'
of spray material was used. This figure including some overspray
works required in the crown.
Staff involved in BAM Nuttall's ongoing tunnel maintenance
contract made best use of the blockade to complete a significant
amount of additional repair work that would have not been
possible within normal midweek night possessions.
Stitching in the Harbour
The 687-yard Dover Harbour Tunnel was constructed in 1863
to connect the stations at Dover Priory and Dover Marine.
It was driven through chalk and lined with four rings of local
yellow stock bricks. Annual examinations had identified deterioration
in the condition of the lining; subsequent intrusive investigations
found voiding behind the brickwork.
Donaldson Associates was appointed to develop remedial options
and carry out the civil and structural engineering design
elements of the project. It proposed the use of radial stitching,
stitching and grouting, and the installation of a 150mm thick
fibre- reinforced sprayed concrete lining using Bekaert Dramix
Steel Fibres. The approach was deemed to improve the overall
integrity and strength of the arch.
The works involved the installation of 720 stitching bars
- each 0.7m long - in the crown and haunches. Holes for the
bars were drilled using a Hilti drill and filled with Hilti
HY-70 resin. Also fixed were 60 dowel bars, 350 L- bars and
80 Fibregrip rockbolts from Weldgrip Geotechnical - these
were fitted using BAM Ritchies' purpose-built rig mounted
on a rail trailer and anchored the concrete lining into the
chalk rock mass behind the brickwork, preventing localised
overstressing. Test Rockbolts were installed within the tunnel
during an earlier phase so bond strengths could be determined.
The analysis and design was carried out using a linear elastic
finite element model in combination with in-house software
developed by Donaldson Associates.
A subsequent phase of work involved the spraying of 35m3
of concrete in a layer 150mm deep, measuring 6.7m x 34m.The
concrete mix was produced by a local BAM Ritchies batching
plant near Dover and delivered by lorry in one-tonne bags.
An RRV and concrete pump completed the concrete's journey
to the works.
Andrew O'Donovan, BAM Ritchies' Project Manager, described
this as "a key project, clearly demonstrating the benefits
of teamwork with all BAM divisions working closely together
to ensure that the full scope of the multi-discipline works
were completed successfully within the limited time available.'
Article courtesy of The Rail Engineer - November 2009
|