|
Slope Engineering
Seaside Special
A few clever tricks have helped keep trains running on time
beside a slippery slope flanking a section of the London to
Brighton railway. Alexandra Wynne keeps her footing to take
a closer look.
Much of the railway line linking London with the popular
south coast resort of Brighton is nestled in sleepy Sussex
countryside. But in recent years, a 200m long and up to 30m
high embankment flanking one section near Haywards Heath has
started to stir causing a number of landslips along its face.
This slope comprises Lower Grinstead Clay, Ardingly Sandstone
and Lower Tunbridge Wells Sand and has historically suffered
from landslips. But Network Rail south east territory geotechnical
engineer Derek Butcher says in recent years failures have
started to happen more frequently. Between May and November
2006 these became severe enough that he had to impose speed
restrictions of 20mph (32kmh), which translated into delays
for passengers.
The railway operator called on contractor Edmund Nuttall
for an emergency response to remove slip material from the
slope and provide toe containment following each of these
movements at the cutting. Although this restored normal line
speeds of up to 90mph (145km/h), the operator wanted to mitigate
the risk of future occurrences and so looked to its Network
Rail Civils Framework (South) to come up with a permanent
slope stabilisation scheme.
In January 2007, geotechnical contractor Ritchies (a subsidiary
of Nuttall) came on board with the framework to carry out
Panda probing work to determine the extent of weathering of
the slope.
This involves using a hammer to hit a rod mounted with a
cone at the end. The head is spring loaded and measurements
are taken to check how hard the hammer hits the rod and how
much of the cone and rod penetrates the ground with each probe.
The contractor carried out 222 of these to 3.5m depths, which
revealed that the worst degradation appeared in the upper
half of the slope. The team passed the information to consultant
Tony Gee and Partners to come up with the stabilisation design.
As a result, since October last year, Nuttall has been carrying
out works according to this plan. This began with re-grading
the top half of the cutting with Ritchies' rope access workers
removing 6000t of material in tandem with long reach excavators
- taking the slope angle down from 50' from the horizontal
to 30'.
One of the recurring problems for the team was how to minimise
further disruption to passengers while carrying out the work.
Nuttall construction manager Guy Keep says this kind of project
typically involves speed restrictions and / or night-time
possessions. These allow only limited windows to work in than
normal daytime operations and would have meant a much longer
period would have been needed to complete the project.
Instead, Ritchies came up with a plan that enables work to
be carried out while the trains continue to run at top speeds
through the affected Copyhold Cutting. This came in the form
of a mid-slope barrier, built prior to main works starting.
This spans the slope laterally and is designed to catch any
debris generated during the works that could otherwise have
fallen on to the tracks.
Vertical Gewi steel bars acted as fence posts and support
the 2m high blast netting that was used to create the barrier.
Workers secured the top of the bars with wire rope attached
to upslope anchors and attached the netting to horizontal
cables. Rock ballast bags and king posts help with containing
any smaller loose material at the base of the slope.
"We considered a toe wall [instead of] dealing with
the problematic slope," says Butcher. "However,
it would have proved costly and difficult to install without
disruption to travellers, and would not have dealt with the
problem slope areas. This idea [for the mid-slope barrier]
will certainly be used on other similar projects across the
country."
In addition to the barrier, one of the rig operators came
up with an idea to improve communication while excavating
with the long-reach rigs. The operator's new plan removed
reliance on hand signals for directing work by mounting a
CCTV camera and microphone near the end of the rig's dipper
arm.
Ridgway Holdings supplied the Komatsu Super Long Reach rigs
- one a PC340-7 with a 22m reach and the other a PC2IO-8 with
a 16m reach. This enabled rig operators and slope workers
to negotiate the working area more effectively, providing
real time images in the cabin of what was being excavated.
The job was made even more delicate by the need to remove
large tree root balls from this part of the embankment while
ensuring none tumbled down the slope and on to the tracks.
Following on from the re-grade, rig operators were able to
carry out the principal stabilisations work beginning with
installing pairs of raking anchors and micro-piles - 54 of
each - along the embankment crest.
These work in conjunction with 200 soil nails installed in
the upper slope using long-reach excavators mounted with an
air-powered drill mast. Each of these 25mm diameter, solid
galvanised steel Gewi bars is installed perpendicular to the
slope down to a depth of 9m. Workers temporarily attached
a tremi pipe to the nail as each is installed to allow the
40Nmm2 grout to flow out from the base of the nail towards
the slope face.
Although typically not as weathered than the less steep upper
slope, sections of the lower section - which reach an angle
of up to 70° from the horizontal - also showed significant
weathering of the weak sandstone. To counteract any potential
problems with these areas in the future, the design here also
included soil nails.
The long-reach excavators were unable to install nails in
the lower slope, so Ritchies switched to using its own designed
and built A-framed Terrapin rigs. Workers installed additional
temporary anchors to provide support for these rigs, which
allowed operators to winch them around the face of the lower
slope.
The lower slope nails comprised a combination of more Gewi
bars supplemented by Geobrugg wire rope anchors for the bottom
row - all of which go in at the same depths and with the same
grout used on the upper slope nails.
The original design had specified using Gewi bars throughout,
but because the space is so narrow at the toe of the slope
the team was concerned that the masts of the Terrapin rigs
could stretch over the railway tracks. This was not an option
when trying to maintain optimum train speeds on the open line.
To avoid this, Ritchies and Nuttall asked Tony Gee and Partners
to help with an alternative. This meant using the flexible
anchors at a shallower angle of 65° from the face allowing
the masts to remain more upright. The wire in these anchors
is more capable of dealing with the bending moment at the
new angle than the rigid steel bars.
On completion of the soil nailing, the long-reach excavator
was due to treat the 2500m2 surface of the re-grade section
with topsoil and grass seeding to improve the appearance of
the embankment. Site workers follow on by laying down North
American Green-manufactured biodegradable matting NAG C350.
This will act to stop erosion of the topsoil while encouraging
plant growth.
To cap off the re-graded area, Maccaferri manufactured rock
fall netting is hung and held in place with face plates. At
the same time Maccaferri's Macmat-R rock netting, combined
with soil erosion matting, is installed across 1000m2 for
the soil-nailed sections of the lower slope. The team is finishing
off the job with rock netting for the less weathered areas
to act as containment for any loose material.
Ritchies project manager Andrew O'Donovan says: "Working
on the bottom of the face so close to such a busy line, while
managing to design a whole system that allows you to move
the rigs about the site, has been challenging. But being able
to come up with this system and have Network Rail approve
the ideas the team came up with has been the most rewarding
part. "
The contracts are worth over £2M for Edmund Nuttall
and £750,000 for Ritchies and all the work was due to
be completed by late March.
Article courtesy of Ground Engineering - April 2008
|