|
Meeting the Challenge
Drilling and blasting operations at Glensanda.
Situated in the West Highlands of Scotland on the north-west
shore of Loch Linnhe is Glensanda, one of Europe's largest
granite quarries. The remote location of Glensanda means the
site is only accessible by sea, the quarry extraction operations
being carried out 500m above sea level.
These operations feed primary crushed rock down a 3.8m diameter
x 300m deep shaft called the 'glory hole'. The rock is then
conveyed out of the mountain, via a mile-long tunnel conveyor,
to a 500,000 tonne surge pile for further processing through
the secondary and washing plants situated at sea level. All
of the quarry's products are transported by ship to UK and
European markets, with occasional shipments made to the US.
Glensanda's remote location and inaccessibility are not the
only unique characteristics of the site; there are many other
challenges and obstacles that have to be overcome to ensure
successful blasting. During the winter months, arctic conditions
are common in the quarry, with temperatures sometimes falling
below -12°C.
Snow drifts are a regular occurrence and, at times, wind
speeds can achieve hurricane storm force 12.
When the quarry is not frozen, water can be an even greater
challenge. The weather can change unpredictably and heavy
showers are commonplace. The site averages 2.5m of rain per
annum, and with very little storage area the run off from
the top of the mountain can increase into white water rapids
as it descends the terrain. This has to be constantly planned
for through development, as benches can easily be flooded.
Groundwater is a frequent problem when drilling and blasting
at Glensanda as it can cause blastholes to collapse and sometimes
makes charging even the good holes difficult, with large amounts
of water present in the shot. Owing to the massive nature
of the site, these problems can be compounded by variations
in the local geology around the quarry. It is essential, therefore,
that every drill hole is of consistent quality to ensure that
they remain intact through the loading process.
The quarry itself, opened up and developed by Foster Yeoman
over the past 25 years, is now operated as Yeoman Glensanda,
following acquisition by Aggregate Industries, part of the
Holcim Group, in 2006.
In November 2007 Aggregate Industries Ltd announced a contract
with BAM Ritchies (a division of BAM Nuttall Ltd) for all
drilling and blasting requirements at the site. The contract
was procured under a comprehensive pre-qualification and tendering
process, recognizing the importance of health and safety,
quality and relevant experience in quarry drilling and blasting
operations.
In shortlisting potential partners, Aggregate Industries
interviewed BAM Ritchies and visited their offices and facilities
to validate proposals contained in their tender submission.
The selection of BAM Ritchies was based on value for money
and their ability to meet the needs of an expanding operation
at Glensanda that will grow over the coming years.
In particular, Aggregate Industries were seeking highly trained
resources, modern equipment and technology and a commitment
to work in a collaborative manner. BAM Ritchies demonstrated
this commitment, which is expected to bring added value to
the partnership at Glensanda over the five-year term of the
multi-million-pound contract.
The awarding of the contract has also firmly established
BAM Ritchies as the major drilling and blasting contractor
in quarries in the UK, and represents the company's largest
contract of this type to date. BAM Ritchies, whose principal
office is located in Scotland, are now well established in
providing this full drilling and blasting package at Glensanda
for the five years from the contract's commencement in December
2007. The operation complements the company's other expanding
quarry activities not only in Scotland, but also in England,
Wales, the Isle of Man and overseas.
In 2007, BAM Ritchies reached the unsurpassed milestone of
over 500 million tonnes of rock blasted since they started
in business in 1966.
So, after the first 12 months of the new contract, how are
the changes benefitting Glensanda? According to BAM Ritchies
and Aggregate Industries, the changes have been notable and
far reaching, resulting not only in increased production and
reduced costs, but also leading to a significantly reduced
carbon footprint brought about by fuel-efficient drill rigs
and higher unit production outputs.
In addition, the use of modern rigs and methods, based upon
industry leading risk assessments and procedures, is helping
BAM Ritchies' commitment to eliminate incidents and accidents
as part of their ground-breaking 'Beyond Zero' behavioural
health and safety campaign, with its clear vision for the
future.
The new developments and techniques cover all elements of
the drilling and blasting operations.
Surveying and face profiling is carried out using MDL's Quarryman
Pro in conjunction with Quarry.4 from Co-Ordinated Survey
Systems. Low cloud and heavy snow are common at Glensanda,
with thick cloud sometimes lasting for days. This can have
a significant impact on face profiling as a typical scan can
take up to 45 min to complete, due to the size of the faces
being fired. Future improvements in technology and software
will make this a much quicker and more efficient process,
with the use of the fast-scan feature on the latest Quarryman
Pro, combined with developments in the survey software, allowing
profiles to be carried out in under 10min, thereby greatly
reducing the time lost waiting for clouds to lift.
Traditionally, the site used in-house drilling with shotfiring
operations carried out by Orica from an on-site bulk emulsion
manufacturing plant. Drilling was carried out by two site-operated
Ingersoll Rand DM-45E rigs, each drilling 168mm diameter holes,
and four ECM 350 pneumatic rigs that were used for production
and development blasting. A total of nine staff were employed,
with the quarry regularly using contractors to ensure production
targets were met. Production was approximately 6 million tonnes
per annum.
Today, however, the quarry requires 7.5 million tonnes of
blasted rock per annum (approximately 150,000 tonnes per week),
which must be suitable for loading using Cat 992 loading shovels.
This represents a drilling requirement of around 3,000m per
week or 150,000m per year.
All of the drilling equipment previously used on site was
decommissioned and replaced by rigs acquired by BAM Ritchies.
The primary resource is two Atlas Copco L7 drill rigs fitted
with COPROD systems, this being the only site in the UK to
operate the COPROD system on L7 rigs. Both rigs are fitted
with the COP 4050-series rock drill providing 40kW of energy
at a frequency of 50Hz through the system's special COPROD
drill string, which comprises an outer guide tube and inner
drill steel that carries the drill's energy to the 127mm bit.
With the COPROD system the L7 is approximately 30% more fuel
efficient in a drilling shift compared with a standard down-the-hole
(DTH) machine of similar size. Having an average penetration
rate in excess of I.0m / min, the L7 has nearly twice the
penetration rate of DTH machines, making the fuel economy
per metre even greater.
Each L7 is capable of drilling 350m in a normal shift, drilling
regulated benches on a varying staggered pattern dependant
on the local geology of the quarry. It is necessary to present
the blasted muckpile in a specific profile to allow it to
be easily and safely worked by the loading shovels, and to
ensure that the material ravels freely as it is dug.
The site also operates an Atlas Copco remote-controlled D9
rig fitted with a top hammer. BAM Ritchies own and operate
the largest fleet of this kind of rig in the UK. The D9 rig
is used for both production and development blasting and has
the ability to drill in some of the most inaccessible areas
of the quarry with little trouble. The operator is able to
safely operate the rig using its remote control unit. In addition,
the rig can be safely anchored using its built-in winch.
The site has its own bulk emulsion manufacturing plant, which
is supplied and operated by Orica. An all-terrain bulk truck
is used to deliver the product to the blast site. The current
requirement is for approximately 2,000 tonnes of bulk emulsion
per year. Excel initiation is used with a variety of timings
to achieve the throw and fragmentation required to achieve
optimum production. Other means of improving the blasting
results are constantly being investigated and the use of Orica's
i-kon electronic initiation system has been trialled to allow
greater control of the blast timings and to improve the resulting
blast pile.
The key to ongoing success at Glensanda is ensuring that
sufficient development work is carried out in line with normal
production, much of which is only accessible by the D9 drill
rig.
These areas must be blasted and opened up to allow production
drilling and the future development of the quarry to take
place. In the coming years it will be necessary to blast the
rock that surrounds the glory hole and to drop the level without
affecting site production and while ensuring that no damage
occurs to the site's only shaft linking the extraction area
with the processing area. Investigation of ground vibration
during blasting will be used to minimize disruption to the
glory hole and to ensure that no oversize material, which
could potentially cause a blockage, is allowed to fall into
the shaft.
All of the drilling and blasting work now carried out at
Glensanda is done by seven BAM Ritchies personnel.
‘With a continually changing and an increasingly demanding
production environment, it is essential that the drill and
blast operations adapt to the needs of the quarry,' commented
Clive Allison, BAM Ritchies' quarry engineer. 'Staying ahead
with advances in technology and improvements within the industry
is key to the operation's success. After a successful first
year that has seen key changes and improvements, BAM Ritchies
will endeavour to meet the challenges of the coming years.'
Article courtesy of Quarry Management - Feb 2009
|