|
Ground investigations underway for
Forth Crossing project
Ground investigations for the Forth Replacement Crossing
project are due to be completed this month.
Transport Scotland appointed Norwest Holst and Ritchies to
carry out ground investigations for the project, and Blom
Aerofilms for topographical surveys. The three separate contracts
have a combined value of £1.7M.
Findings from the surveys will provide information on the
contours of the land and ground conditions in the area to
inform the proposed bridge and connecting road network designs.
Forth Replacement Crossing project manager Lawrence Shackman
said: "Following the government's announcement in December
to build a multi-modal, cable-stay bridge across the Forth,
work has been progressing rapidly and these surveys are the
next key milestones in the project.
"A team of about 40 geotechnical engineers, geologists
and drillers are undertaking ground investigations on the
northern and southern banks of the Firth [a narrow sea inlet]
of Forth. The findings will be used by our engineers to progress
the preliminary designs for the bridge and connecting roads."
Ritchies, whose l2-week contract is worth £800,000,
is working on
the south side of the Forth. It has deployed four cable percussive
rigs and five rotary rigs to the site from its Scottish Kilsyth
base. Boreholes are being drilled to a maximum 80m using a
combination of cable percussion boring followed by rotary
drilling, with extensive use of rotary wireline drilling.
Norwest Holst won the ground investigation contract for the
area north of the Forth. The works, which are expected to
last about nine weeks, involve excavating trial pits and boreholes
in the vicinity of the M90/ A90 road corridor.
Ecologists and archaeologists have accompanied the teams
on site.
Somerset-based Blom Aerofilms began aerial photography for
the topographical surveys at the end of March.
The engineer is a Jacobs-Arup consortium. Construction of
the £3.2bn to £4.2bn project (at 2016 out-turn
prices) is expected to start in 2011 and take five and a half
years to complete.
Article courtesy of Ground Engineering - June 2008
|