|
A Rock and a Fast Places
Scotland's A77 is getting an upgrade that. includes a soil
nailing solution next to a busy road. Damon Schunmann reports.
As the An snakes its way along Scotland's west coast, it
frequently dips and rises through areas with exotic names
such as Hagstone (see Hagstone mythology), just north of Caimryan
and almost 100km south west of Glasgow.
Here, there is a hive of activity surrounding a project to
re-profile an existing natural slope to allow the widening
of the road from two lanes to three along a 2km section. This
will include a new climbing lane for slower vehicles.
The excavated face is being stabilised by soil nailing with
1450 linear metres of slope being treated along a stretch,
with heights varying up to 15m and slope angles up to 60°.
But before work could begin the site needed the all-clear
on any ordnance that may have been present. Main contractor
RJ McLeod agent Andy Gillan explains why: "Finnarts Bay
[near the site] was a staging post for Second World War convoys
going over to the US so there was a lot of anti-aircraft bunkers
near the site. We had to check them for ordnance and munitions,
but fortunately we did not find anything."
Once the geotechnical work began in earnest it consisted
primarily of the excavation and soil nailing going hand in
hand. This sees RJ McLeod benching down to allow the stabilisation
of the slope and access for plant and equipment. Subcontractor
Ritchies is drilling and installing the soil nails as the
reprofiling progresses.
Ground conditions consist of glacial till overlying greywacke
(a variety of sandstone), which is both weathered and competent
rock.
Prior to installing the working nails, Ritchies put in and
stressed 10 test nails to confirm the design and installation
process (see Test nails). By the time the scheme completes,
site workers will have installed a total nail length of 20km.
Six machines are doing this work including a pair of Boart
Deltabase DBl20s as well as a 100, a Casagrande C6, an Altlas
Copco A65, and an Ingersoll Rand Airtrack rig.
Drilling is achieved using down the hole (DTH) hammers and
air flush. The nails are Dywidag GEWI Bars, double corrosion
protected. Both the annulus between nail and corrugated sleeve,
as well as that between sleeve and hole, are simultaneously
grouted into a l25mm diameter hole. These holes vary in length
between 2m and 16m. Grout is neat CEM 1 having a design 28-day
strength of 40N/ mm'. It has a water / cement ratio of 0045.
Selected nails are tested to 210kN by Ritchies engineers to
ensure the specification is met.
Each nail is fitted with a 400mm by 400mm galvanised head
plate that secures the surface facing of Maccaferri Macmat
R, which acts as a passive retaining system. This is initially
secured at the top when the first nails are installed and
then unrolled as the work progresses. Gillan says: "The
Macmat R rolls are pinned at the top by permanent 1m Duckbill
anchors and we can unroll when [Ritchies senior geotechnical
engineer] Stuart Jackman is working two rows of nails below
us."

RJ McLeod business development manager Jamie
Corser says the main problem is access on a site that is stuck
between a rock and a fast place. "It's adjacent to a
live carriageway," he explains," with Jackman adding:
"It really is like a sliding puzzle when moving everything
about."
The main contractor also had to bring in reduced
tail swing excavators for the first rows of nails to prevent
the tails hitting the slope's surface at the top where the
benches were narrowest.
Although at the start of the job the ground was relatively
free of water, rainfall prior to GE's visit made for more
challenging conditions.
Jackman says: "At the south end is a gulley
of glacial till and after a couple of days of rain it's unbelievable.
The water gets between the glacial till and the rockhead about
7m to 8m in and when we drill into this zone the water runs
out until we grout it." This has required additional
temporary works in places of wooden panels to protect the
face as it can become destabilised.
RJ McLeod is putting excavated material to good
use on the site with intact rock acting as Type 1 carriageway
sub-base. Weathered rock is getting reused as general fill
Class 1 to build the road embankment on another part of the
An, a 1.4km long realignment section about 6.5km further to
the north at Glennapp. Gillan says the intention is to use
all excavated material between the two sites. Corser adds:
"It's economics that you don't want to be taking it to
landfill, but the theory on any job is not to do this [take
it to landfill] for the good of the planet."

Test Nails
Prior to the installation of the working nails, 10 test nails
were installed in various positions throughout the site to
approve the assembly and installation methods, and carry out
proving tests to validate the design. The test nails were
drilled, using a Deltabase 120 off the access road in the
slope above the production face. They were installed to the
following depths:
- TN01 and TN03 - 3m into glacial till, fully bonded
- TN02 and TN04 - 2m into glacial till, fully bonded
- TN05 - 5m total length, 1m bond length in non-intact rock
- TN06 - 4m total length, 1m bond length in non-intact rock
- TN07 - 5m total length, 1m bond length in non-intact rock
- TN08 - 5m total length, 1m bond length in intact rock
- TN09 - 10m total length, 1m bond length in intact rock
- TN10 - 3m total length, 1m bond length in intact rock.
Once the grout cube results had returned with
the 40N/mm2 strength achieved, Ritchies carried out proving
tests. These were done using a 300kN hollow ram jack and hand
pump. The reaction frame was made up of timber sleepers and
a fabricated steel frame.
Elastic extension was measured using a dial gauge positioned
on a tripod frame. A circular steel plate was attached to
the end of the nail for th.e needle of the dial gauge to bear
against.
A timber rail was erected in front of the reaction frame to
monitor any displacement of the head plate (see below).

Article courtesy of Ground Engineering - June 2008
|
Parties
Involved
Client:
Transport Scotland
Engineer and client's representative:
Atkins
Designer/consultant:
HalcrowGroup
Design checking:
Tony Gee and Partners
Main contractor:
RJ McLeod
Geotechnical subcontractor:
Ritchies
Ritchies agent:
senior geotechnical engineer Stuart Jackman, whose experience
of this type of work includes the soil nailed east catchments
at Gibraltar where Ritchies installed over 8000 soil
nails.
|
Contact,
Value and Programme
- Main contract value £l8.7M
- Soil nailing sub-contract £1.245M
- Contract conditions are ICE (Institution of Civil
Engineers) design and build
- Programme duration is 18 months with soil nailing
planned to take 19 weeks
- Work began on site on 15 October last year with the
soil nailing commencing on 7 January
- Ritchies was due to finish by the end of May, depending
on how the excavation progressed. |
Hagstone Mythology


A hagstone is a stone
with a hole in it that is hung in stables and homes to keep
away witches or hags at night. If hung on the bedpost, it
supposedly protects the sleeper from having a hag ride one's
chest and causing a nightmare. Hung in a stable, it prevents
witches from riding horses all night to exhaustion.
Plant and Equipment
- Rigs used are two Deltabase 120s and a 100 with Eurodrill
5012 top hammers, a Casagrande C6, an Atlas Copco A65 and
an Ingersoll Rand ECM (extended crawler mounted) 350
- Drilling is generally cross carriage
- Both top hammer and down the hole hammers (DTH) are being
used, depending upon ground conditions and the need for casing
- The casing systems include the Boart Longyear 152.4mm diameter
system with top hammer and Symmetrix NOT Set 120 using DTH
hammers.

Working Nails
and Surface Facing
The subcontractor is installing soil nails at 1.5m centres
(vertical and horizontal) into the new slope cut at 600 from
the horizontal. Criterion for the length of the soil nails
was as follows:
- Soil nails, where the overburden and non-intact rock was
less than 5m thick, are installed into a 2m intact rock socket.
Bars are 25mm in diameter
- Soil nails, where the overburden and non-intact rock was
more than 5m thick, are installed into a 3m intact rock socket.
Bars are 28mm in diameter.
The first row of nails is positioned about 0.5m down from
the top of the original slope. From there, a row of nails
is being installed every 1. 73m, slope distance, down until
there are two rows of 2m long nails into intact rock. They
are double corrosion protected bars. The nails are assembled
onsite and grouted insitu.
The original specification was to have only the top 3m of
the nail galvanised. This was thought to be difficult to manage
on site and so the decision was made to purchase all bars
with galvanising throughout.
The soil nail is assembled with wrapround spacers fixed to
the bar 0.5m from the bottom end and then every 2m to the
top. Site workers then place this bar into the ducting while
adding lantern spacers on to the ducting, 0.5m from the bottom
end and then every 2m to the top.
The nails are then inserted into the 125mm diameter borehole.
Depending on the length of the nails, additional sections
are added as it is installed. Ritchies then grouts inside
and out.
A passive retaining system provides the surface covering with
the head plate detail then assembled to complete the system.
|