|
Safe as houses?
Historical mining often results in subsidence. A housing
estate in Hatfield, UK, faced this issue until remedial work
corrected the problem.
In the early decades of the 20th century, the area surrounding
the Briars Lane suburb of Hatfield, UK, was the site of chalk
mines - shallow underground workings in the geological horizon
known as the Cretaceous Upper Chalk. The only record of the
mine is a single kiln marked on a historic Ordnance Survey
map.
Between six and 20m below the surface is a labyrinth of shafts
and horizontal workings from which the chalk was extracted.
)-here appears to be no specific mined horizon, nor any directional
trend, and therefore the assumption is that the miners followed,
probably by colour and softness, a particularly pure chalk.
The workings were typically two metres wide and a maximum
of 3.5m high. Up to four levels were tunneled in any one location
but their orientation appeared completely random. Mapping
of the workings was made doubly difficult by frequent roof
collapses. As the workings were artisanal and unmechanised
there are no existing plans of the tunnels and stopes, nor
of the amount of material mined. The last workings were in
the 1920s.
New use
A decade later the area above the chalk became the site of
council housing, but it was not until 1978 that the first
subsidence was recorded in an area 3.6x4.6m. In 2001, a six
metre-deep crownhole developed, collapsing a footpath and
damaging a property. The risk of further collapses required
action, highlighted by the evacuation of some houses and a
school in 2005.
The local authorities, Welwyn Hatfield Borough Council and
Hertfordshire County Council, together with English Partnerships,
the national regeneration agency, began remedial work. The
objective was to provide a solution that would allow safe
occupancy of the site, ensure minimal future ground movements,
remove site blight and restore public confidence, while minimising
disruption to the community.
It is usual in civil engineering projects for the work to
be specified by an overseeing agency and let to a contractor
to carry out the work and take the operating risk. In this
case, the risk remained with the client allowing the best
technical solution to be developed and implemented by three
UK companies — Hyder Consulting, the designer and contract
supervisor; the contractor BAM Ritchies, and their consultant
RJM Ground Solutions.
Probing questions
The first challenge was to ascertain the extent of the chalk
workings and volume of voids. An extensive phased ground investigation
was begun in August 2006 with dynamic probing to 20m. The
probes comprise a steel rod driven into the ground to measure
the penetration rate for each calibrated blow. The lower the
resistance, the greater the penetration. Although crude, the
technique allowed rapid progress with 1,589 holes completed
in a few weeks with minimal interference to residents and
traffic.
In addition to the dynamic probes, 82 boreholes were drilled
in locations identified by the probes for a more detailed
view. The boreholes were used to insert CAL-S downhole lasers
and CCTV. Microgravity surveys completed the underground picture.
The survey work revealed extensive voids where mining had
taken place and also areas where subsidence had weakened the
ground. These required separate solutions, bulk infilling
of the voids and compaction grouting of the weak areas. Again
minimum disruption to residents and their property was the
prime consideration.
Normally cement is mixed on site with a bulking agent such
as pulverised fly ash (waste from power stations), however,
the Upper Chalk is an aquifer and therefore leached metals
within the ash may have contaminated water. The chosen filler
was ground limestone, which is chemically similar to chalk.
A foaming agent from a mobile plant was also used to infill
the voids and combined with the ready- mixed cement brought
to the site to avoid the associated noise and dust.
In the compaction grouting a three-metre square grid over
targeted features was the operational level. With bulk infilling,
the objective was to fill the void without over pressuring
and to ensure adequate flow was achieved to reach distant
parts. Down hole CM/ and dynamic probing were used to monitor
the void filling.
A thin cement mix was pumped out at high pressure as the
borehole probe was gradually withdrawn from the base of the
hole. An inflatable packer system ensured that the grout remained
in the hole. A Lutz meter was used to monitor the flow and
reconciled against input to the grout plant. The danger of
infilling and grouting is that the disturbance related to
drilling and pumping of the cement mix may cause ground movement.
To monitor this, the consortium carried out structural leveling
surveys and installed automated tiltmeters on buildings. These
instruments were linked to the Internet and could also provide
immediate notification of movement via a mobile telephone.
This treatment work commenced in August 2007, with site works
completed by the following March.
To ensure confidence in the remedial work a series of validation
exercises was carried out. The results of these exercises
and data from the initial ground investigation survey were
entered into a Rockworks computer database.
Accessing the data allowed a continuous review of progress
and enabled real-time discussion of the effectiveness of the
works onsite. Of specific note was the integration of the
results of 375,000 dynamic probe blow counts and borehole
records that provided an interpretation of the voids and disturbed
ground. These data were validated against the input of grout
and foamed concrete measured by the Lutz meters.
The success of the treatment was checked against drilling
records of any large voids and excess grout intake during
pumping, both in total and vertically in the hole. Another
251 dynamic probes were taken post-treatment. Although the
technical aims of the project were met, a greater satisfaction
resulted from the reaction of the residents who were allowed
to move back to the area in August 2008. Since then, properties
have been bought and sold consigning the blight over Briars
Lane to history.
Article courtesy of Materials World - May 2009
|