|
Site Investigation, Testing and Monitoriny
Holey War
A quiet suburban street in Hertfordshire is at the
hub of a major effort to prevent homes being swallowed up.
Alexandra Wynne finds out what is being done to protect the
threatened buildings.
Abandoned and unstable chalk mines beneath Briars Lane in
Hatfield have been gradually making their presence known for
almost 30 years. But now a new project with a twofold approach
is under way to stop future ground collapses.
The first known subsidence to hit the street occurred at
Briars Lane Infant School in May 1978. A 3.6m by 4.6m diameter
hole opened up in the school grounds and borehole investigations
at the time suggested dissolution in the underlying chalk
as the likely cause.
But further events in Briars Lane continued to cause problems
for homes, pavements and gardens over the next three decades.
Structural problems were sufficiently severe in places that
in 1986 it was decided four pairs of semi-detached properties
would be demolished.
Hertfordshire County Council and Welwyn Hatfield Borough
Council were able to secure funding from English Partnerships
to deal with the problems and instructed engineer Hyder Consulting
to begin site investigation work in late 2004.
It drilled 45 boreholes as well as doing microgravity surveys
in a six month project to determine what was causing the problems.
It also carried out a total of 1800 dynamic probes. All the
investigations helped reveal the presence of up to 2m wide
voids.
The work also helped establish whether there were any offshoot
tunnels and gave a clear indication of where the perimeter
should be for the follow-on bulk infilling work. Rig operators
worked within circular perimeters around each of the houses
in the areas affected by subsidence.
The results of the investigations showed mines appearing
at depths of between 7m and 20m in low grade upper chalk.
This is overlain by up to 5m of glacial clays, sands and gravels.
Site workers used CCTV cameras inside the boreholes that
provided 3600 images and revealed six large voids pointing
to a network of mines. Hyder senior geotechnical engineer
David Jones says these images showed the mines had suffered
extensive roof collapses.
He says desk studies and anecdotal evidence suggest the chalk
mines were in operation from the 18th century to the Second
World War - some years after the site was developed for housing
in the late 1930s.
Following discovery of the 2m to 4m high mines, comprising
a series of galleries up to four levels, the two councils
awarded a £4M contract to contractor
Ritchies to treat the abandoned mines. This was based on
Hyder's design and the consultant produced a 3D mine model
to monitor the work.
Ritchies started work on site shortly after being appointed
in July and is using a two fold approach bulk foam infilling
and compaction grouting - to stabilise the ground. The voids
range in size from about 50m3 to 1000m3 but Jones says it
is difficult to be sure how large they are because the mines
and offshoot tunnels interconnect.
Gaining access to the site has been one of the biggest challenges
the team has faced. The work has been made easier by the school
closure (it was relocated 18 months ago), the temporary re-housing
of some residents and the closure of the road at one end.
However, many residents have stayed put and causing minimum
disruption to them has made it more difficult for site workers
to stabilise the ground beneath their feet.
"There's a lot of plant working in a confined space.
It would have been easy for us to do the work if we could
have flattened the site," says Jones. "But it's
not that simple because these buildings need to be re-used.
"
As a result Ritchies is using rigs that can stand away from
the property while completing the work. Two of its own rotary
drilling masts are attached to Hutte tracked excavators, which
are supplemented by two Casagrande rigs. The masts have a
long reach capacity to make it easier to get over obstacles
such as garden fences.
Over 750 holes need to be drilled to complete the stabilisation
work. Site workers pre-drill the between 100mm and 150mm diameter
holes using flighted rotary augers before inserting by hand
3m lengths of plastic casing down to depth for the large open
voids.
Ritchies site agent Andrew O'Donovan says the chalk is of
such a consistency - similar to putty - that the holes stay
open, but that the casing is necessary to help control where
the grout goes. This ensures it does not get caught in the
upper layers of soil before reaching the open voids.
For this part of the job a high cement grout was mixed with
a protein-based foaming agent just before being pumped into
the ground. This creates a lightweight fill material that
has about one quarter of the weight of concrete. Site workers
have completed the bulk infilling using a total of 1420m3
of grout - the equivalent volume of 18 double-decker buses.
The works are being staged to minimise disruption to residents,
the idea being the less time they are out of their homes the
better. Work is now continuing on the next portion of the
contract - to compact the loose ground surrounding the voids.
The team is expecting to use a total of about 4500m3 of compaction
grout mix for this. Site workers pump the grout into the ground
at decreasing pressures as the 100mm diameter hose retreats
from the base of the hole towards ground level. Typically
the grout is injected down to a maximum of 25m and pumping
stops 5m below ground level.
The pressure ranges from 40bar to 5bar at the pump outlet
as the hose is extracted from the ground. O'Donovan says Lutz
monitors are being used at each of the injection points to
monitor the pressure and flow of the grout.
The final part of the contract will follow on from this work
and is again designed to cause minimise disruption for residents.
As well as being able to do injection work at a distance
away from properties, the long-reach excavators will do about
one-third of the injection grouting at an angle of 30°
from the vertical.
These holes will reach further than the vertical ones - a
maximum of 30m into the ground - to get to the right depth
for compacting the loose material. This technique will allow
site workers to compact ground directly beneath the homes
without intruding on the properties themselves.
Monitoring on site is being done in a range of ways. To check
the compaction grouting, site workers are doing more dynamic
probing between injection holes to check it has sufficiently
stabilised the ground.
In addition, two surveyors are on site to check level monitors
that are placed around injection holes, ensuring there is
no local ground heave that could be detrimental to surrounding
homes.
Movement of the buildings directly affected by the works
is being monitored by 57 optical survey points that are checked
manually and 81 automated tilt meters. These have been installed
on 15 buildings and the latter have been set with alarm limits
of 2mm and 4mm. At this point text message alerts are sent
to on site and off site team members.
O'Donovan says the tilt meters have registered some movements
usually m the region of 0.lmm - but adds that this is typically
attributed to thermal expansion.
The work is due to be complete by the end of the year at
which point a landscaping contract will follow to reconstruct
paving and improve the look of the street.
Article courtesy of Ground Engineering - Nov 2007
|