|
Sprayed concrete for the railway infrastructure
Sprayed Concrete has been a tried and tested method of improving
the Railway Infrastructure over many years. However, the drive
to improve Health and Safety within both the construction
and rail industries has resulted in a variety of methods being
developed to meet this goal. Traditionally Sprayed Concrete
works have been undertaken by a 'nozzleman' controlling the
water addition, and therefore the quality of concrete, to
a stream of dry materials to apply Sprayed Concrete to railway
tunnels, bridges, retaining walls, arches and other structures.
The skill and experience of operatives is paramount to the
successful completion of projects and Certification by ClTB
and the UK Sprayed Concrete Association should be a pre-requisite
in all cases. The use of prebagged blended materials has given
great flexibility in terms of material transportation and
storage, and can be of benefit in possession works or where
construction work has to be undertaken at geographically remote
sites.
St Thomas Viaduct, Exeter
An example of Sprayed Concrete for the railway infrastructure
improvement using manual Sprayed Concrete application was
the strengthening works undertaken by BAM Ritchies to two
brick rail arches in Exeter during Christmas 2006. The brickwork
forming the arches had suffered over a number of years from
water ingress causing mortar loss, brickwork spalling and
loss of individual bricks, giving cause for concern for the
long term stability of the arches.
A design was drawn up to reinforce the arches by application
of 1S0mm of Sprayed Concrete to the arches incorporating a
layer of A393 reinforcing mesh, fixed in place with resin
fixed dowel bars, within the concrete layer. The fixing of
strips of 'egg box' waterproofing membrane was incorporated
to ensure future water ingress through the arch brickwork
would be channelled into the existing arch drainage system.
All preparatory works and the construction of a concrete
sidewall were
undertaken during normal day shift working in the build up
to a 'wheels free' possession starting at 2300 hrs on December
24th. With the potential for low night time temperatures being
recognised on site, all works were undertaken in tented and
heated areas to ensure early strength gain of the Sprayed
Concrete with no possibility of frost damage.
To ensure a high early strength gain, preconstruction testing
was undertaken to confirm early strength development of an
accelerated pre-bagged Sprayed Concrete material, with the
material giving a 10 N/mm2 compressive strength at 24 hrs.
The arch spraying was undertaken within a six hour period
using two BAM Ritchies spray teams, allowing the 'wheels free'
possession to be lifted following the Christmas break.
Travis Street, Manchester
The introduction of remotely controlled robotic sprayed concrete
applicators allows the use of ready mixed concrete materials,
with quality control being exercised at the ready mix plant,
and in addition has allowed the reduction of risk to the sprayed
concrete 'nozzle man'. The operative is physically removed
from the area of application, but the process still relies
on the skill and experience of the operative to control layer
thickness during Sprayed Concrete application.
At Travis Street in Manchester, adjacent to the main line
Manchester Piccadilly Station, two brickwork arches required
strengthening due to movement through the arches resulting
in brick loss and arch stability concerns. The re-instatement
design called for a construction of new arch sidewalls including
footings, to support a new 400mm thick concrete arch - all
in 40 N/mm' strength concrete.
The footings and wall were constructed in traditionally reinforced,
shuttered and poured reinforced concrete. The arches were
designed to incorporate two layers of 10mm reinforcement matting
together with the addition of 40 Kg/m3 of stainless steel
fibres in the concrete mix to provide additional load bearing
capacity for the arch section. Prior to any reinforcement
fixing, a layer of drainage membrane was fixed to each arch
to provide a waterproof barrier between the existing brickwork
and the new concrete construction.
To enable an economically viable construction method, a Sprayed
Concrete technique was chosen using a 10mm aggregate ready
mixed concrete, incorporating the stainless steel fibres,
super-plasticiser and hydration control additives. To enable
overhead application, an alkali-free accelerator was added
at the spray nozzle, dosage being controlled by automatic
monitoring of the Sprayed Concrete pump output.
A remotely controlled robotic applicator was employed on
site by BAM Ritchies to allow the 400mm Sprayed Concrete to
be applied without the need for access to the arch and to
remove the 'nozzleman' from the risk area beneath the freshly
applied arch concrete.
The movement of the robotic applicator is controlled by joystick
operation, the control of which requires a great deal of skill
on the part of the operator to guide the Sprayed Concrete
jet along the wall whilst optimising the sprayed concrete
thickness and minimising waste. The operator must practice
a long time to master manual control of the process to a satisfactory
standard. Quality control of the material, however, is similar
to that exercised in normal ready mixed concrete operations.
Both arches were completed during normal day shift working
during normal train operations.
The future for Sprayed Concrete application
The recent introduction in Europe of computer controlled robotic
nozzle applicators with laser thickness control, has taken
the development of sprayed concrete application a step further
and is awaiting introduction into the UK rail industry. The
laser controlled robotic nozzle uses laser scanning to provide
both preapplication profiling of the tunnel or arch to be
sprayed and automatic layer thickness control during Sprayed
Concrete application, thereby eliminating the need for operator
control of the spray applicator.
The laser robot is computer controlled and enables the system
to measure the existing profile of a tunnel to within Smm,
using a laser scanner over a selected areatypically a three
to four metre long section of tunnel. The operator selects
an area of tunnel to be scanned using a red dot laser marker
integrated in the sensor. The sensor can scan up to 3000 and
scans at 200mm centres longitudinally and radially, providing
an accurate computer file representation for the robot control
processor.
Using the stored profile information the processor controls
the sprayed concrete pump operation and nozzle orientation
over the selected area. The nozzle orientation and position
is automatically updated for each of the pre-measured 200mm
centres. This process allows the Sprayed Concrete layer to
be applied to the correct thickness over the full tunnel profile.
The accuracy of thickness control is both excellent, with
tolerances of +j- Smm achievable and, more importantly, repeatable.
The system has been used to line over 28,000 m' of tunnel
in the Netherlands and presents an exciting opportunity for
its future introduction into the UK, thereby improving not
only the quality of Sprayed Concrete within the railway infrastructure
works, but also the Health and Safety of the work force. Fires
in tunnel do occur, as demonstrated recently in the Channel
tunnel. The use of plastic fibres in the sprayed concrete
mix increases the durability of sprayed concrete linings in
such situations.
Increasing use of steel fibres provides the opportunity to
reduce the use of conventional reinforcement, mesh and lattice
reinforcement. Modern additives reduce the aggressive nature
of cement/additive rich mixes so reducing the risks of alkaline
burns to operatives.
This article has been created by Bill Jones, Contracts
Manager BAM Ritchies
|