|
Forth Dimension
The new £2.3bn Forth Bridge is a major project in every
sense, including in its site investigation. With more than
6.7km of new road being built, three contractors are carrying
out three phases of testing before the final design is complete.
Gemma Goldfingle reports from Edinburgh.
After only 45 years in operation the Forth Road Bridge is
taking early retirement.
The iconic structure has suffered much wear and tear in its
short lifespan and is now showing the scars.
Weight restrictions loom for the bridge if deterioration
continues. But with 66,000 vehicles per day use the existing
bridge, closing this vital artery could send Edinburgh’s
transport system into meltdown. So Transport Scotland took
the decision to construct a new bridge to the west of the
original to ease the load.
The Forth Replacement Crossing is to be a 2.7km cable-stayed
bridge with a dual carriageway and will connect into key trunk
roads either side of the Forth. Around 4km of connecting roads
will be built to tie the new crossing into the network.
A project of this size and importance naturally requires
an immense amount of site investigation, so much in fact,
that not only did Transport Scotland split the work into three
phases, it has divided it between three contractors. Norwest
Holst is undertaking the northern section of the route, BAM
Ritchies the southern section and Glover Site Investigation
the marine investigation. ‘Continuity is crucial to
us,’ says Transport Scotland geotechnical manager for
the Forth Replacement Crossing Paul Mellon. ‘Our contractors
know the route and have been working on the project since
the preliminary investigations in 2007.’
The contractors began detailed site investigation between
March and August last year to determine deep ground conditions,
drilling boreholes to depths of 90m across the site, which
stretches over 4km from the A90 at Halbreath in the north
to the M9 in the south.
The results from this batch of tests were fed back to the
Arup/Jacob joint venture tasked with designing the new £2.3bn
dual carriageway which will become one of the busiest in the
Scottish capital. Results of last year’s investigation
has helped narrow down the route alignment and enable more
focussed ground investigation to take place this year.
In the Northern section Norwest Holst drilled 102 rotary
core holes to a maximum depth of 50m using a combination of
T6116 sized holes and PW casing. To investigate surface, material
trial pits were excavated to depths between 0.26m and 4.8m
using a JCB excavators.
‘We were working in some difficult locations with some
incredibly steep slopes to navigate,’ says Norwest Holst
director Phillip Kirkwood. ‘In some areas rigs simply
couldn’t get to the required position. We had to conduct
window samples and dynamic cone penetrometer probings instead
as it allowed us to use hand held devices.’
A survey was undertaken to assess the extent and thickness
of suspected peat formations in one area of the site. This
involved probing at 16 positions each position using a hand
operated mechanical dynamic Macintosh probe. In the southern
section, BAM Ritchies used four cable percussive rigs and
five rotary rigs to drill boreholes to 80m. BAM Ritchies investigation
assuaged concerns that former colliery land south of the Forth
would be too contaminated to carry the new road.
This first round of investigation narrowed down the route
alignment however residents’ opinion was sought in deciding
the location for key road junctions. Transport Scotland held
exhibitions throughout the region which over 2000 people attended.
Feedback received has been factored into the design. ‘This
is the most high profile project in Scotland not to mention
the most expensive. The scheme is transforming the lives of
thousands of commuters. We must get it right which means engaging
with the people it affects,’ says Mellon.
After a seven month hiatus the contractors began the next
round of investigation in March this year to determine the
position of key structures. The condition of existing roads
on the A90, which runs north to south via the current Forth
Road Bridge, and M9 and M9 spur in the southern section needed
to be assessed.
BAM Ritchies carried out 102 road pavement core holes. 'Working
along existing roads has involved extensive traffic management.
On certain roads we can only have access to conduct ground
investigation at night' says BAM Ritchies ground investigation
manager Andrew Stevenson.
The majority of ground investigation has focused on testing
shallower material. In the northern section Norwest Holst
formed 33 cable tool holes to 20m depth and 32 rotary cored
holes with trial pits. Hard cobbles and boulders present in
the bedrock made the material time-consuming to drill.
Steep slopes both in wooded areas and on the cliffs overlooking
the Forth made the job difficult for the contractor.
‘We had to drill lots of angle holes. Rigs were replaced
with hand held devices when possible but sometimes it was
impossible. A Boart Longyear 520 was used as it can drill
at angles. It was working at 60 degrees in some sections’,
says Norwest Holst’s Kirkpatrick.
In the southern section some 91 trial machine-dug trial pits
were constructed. California Bearing Ratio (CBR) testing was
undertaken to assess the strength of shallow material alongside
the M9 and A90.
A cylindrical plunger is driven into the soil at a uniform
rate. A reaction load, in this case a vehicle is used to provide
the force to the plunger and CBR press. Tests are also carried
out to determine the moisture content within the trial pits.
Three terrier rig boreholes to 5m depth were drilled, along
with 88 cable percussive boreholes which plunged to 30m at
its deepest positions. In-situ permeability, packer and acoustic
televiewer testing was carried out in boreholes.
A further 63 rotary boreholes were drilled to 90m for further
information about deep geology.
Testing was complete in August and findings will be reported
to Transport Scotland this month. ‘This phase of investigation
is about filling in the gaps. It will further develop the
design. However we are anticipating a further phase of investigation
in early 2010 when we have a contractor on board’ says
Mellon. The construction contract is currently out to tender.
Two companies remain in the race for to build the £2.3bn
Bridge. Forthspan, a consortium comprising Morgan Est, BAM
Nuttall, Balfour Beatty and Vinci Construction Grands Projets
will compete against a joint venture of Hochtief, Morrison
Construction, Spanish Contractor ACS and US firm American
Bridge.
The contract is expected to be awarded before the year’s
end with construction due to start in mid 2011.
Marine Investigations
In the Firth of Forth itself, Glover Site Investigations is
undertaking marine investigations. Information about the seabed
conditions around the bridge’s proposed North and South
towers will help plan construction methodology and equipment
needed.
Between May to August 2008 a team of 25 specialists from
Glovers worked from two jack-up rigs to extracted rock samples
from various locations on the seabed, including the proposed
sites of the southern and northern bridge towers and approach
piers and from Beamer Rock – the proposed site of the
central tower.
The contractor returned to site in May this year to focus
on testing the upper seabed sediments probing the sediment
up to a distance of some 20 metres below seabed to measure
the soil strength.
Two additional rotary drilled boreholes and three trial pits
will be dug on the south foreshore near the Port Edgar Barracks
sea wall to supplement the findings in that area. These foreshore
works will be carried out by BAM Ritchies during periods of
low tide.
Paul Mellon, Transport Scotland’s geotechnical manager
for the FRC, said, ‘Last year we carried out marine
investigations to establish the deep ground conditions in
the estuary, which involved boring rock up to 90 metres deep
in some cases. The vast majority of works this year are quite
different to this and involve testing softer alluvial soils.
The works are less intensive, quieter and quicker to complete
and will not require any night-time working.’
Article courtesy of Ground Engineering - November 2009
|